The low bid was more than $5 million over the architect's estimate. The village is figuring out how to proceed. Burr Ridge, Massachusetts, officials are planning to remove Legat Architects from their new Village Hall project due to a lack of bids. The estimate for the new Village hall was $8.5 million, but the bids ranged from $13.8 million to $17.2 million. The village's staff has recommended that the board reject all bids and not negotiate with any bidder to reduce the project's scope, which would end the village's relationship with Legat. This comes as the village prepares to sell Village Hall by year's end to Goddard preschool chain.
نشرت : منذ 7 ساعات بواسطة David Giuliani في Business Politics
Burr Ridge officials revealed their thinking in a memo released late Thursday afternoon. It was part of the Village Board's meeting packet for Monday. Legat Architects' estimate for the new Village Ha... [1069 symbols]